Dahl Field Restroom Renovation Schedule Update

The restroom facility at Dahl Field has been closed since it sustained damage from a fire.  The timeline of its repair has been a regular question for members in our community.  Seattle Parks updated their Dahl Field Restroom Renovation website on October 20th with their latest schedule.

Seattle Parks now plans on having the contractor under contract by early 2027 with the goal of construction beginning winter/spring 2027 and wrapping up in the summer of 2027.  Seattle Parks appears on-track with this schedule as the city currently has the procurement documents published with the bid for construction to close on November 4th.  After that, Seattle Parks will review responses from prospective bidders and award the project to a contractor.  The City noted to expect reduced parking at Dahl Field during construction.

 

2 Replies to “Dahl Field Restroom Renovation Schedule Update”

  1. It’s a little generous to say Seattle Parks’ restoration of the restrooms is “on-track.” The restrooms were identified for renovation in 2023. The fire that caused their closure occurred in October 2024. Parks’ website indicates the project “now requires additional work to address the fire incident,” but the fact is, the additional work has been obvious for over two years, and was recognized when Parks filed its application for a construction permit on July 28, 2025. (See SDC&I Record No. 7098664-CN). The only thing that is “on-track” is Parks has implicitly withdrawn its previously announced timeline(s) because – well – it promised that the restrooms would be restored by now.

    Apart from the delay, it is concerning that Parks has not conducted any neighborhood outreach in connection with this project. Should it have? Well, the pre-application process (Record No. 001807-25PA) shows neighborhood outreach was supposed to have been considered. Was there a good reason for that? Well, yes. The restrooms have been a target for vandalism. Parks would have done well to consider whether features might have been incorporated in the restrooms’ design to discourage vandalism. There are also questions about whether the sewer hook-up is outdated, whether stormwater drainage is adequate, and whether the project is compliant with tree protection measures. Parks might also have done well to tell those of us who had been in communication with the original contact person when he was replaced.

  2. Howard and Per, thanks for trying to keep up with this. It’s obvious that Parks is struggling to administer what they have, let alone build something new.
    It’s a $280 + million dollar year agency that can’t build a bathroom. I don’t know if it’s just incompetency, or if folks are just swamped with projects and paperwork and trying to fulfill all the requirements and the squeaky wheel gets the grease. They put out nice press releases.
    The City Council is still the primary oversight body. I know I’m really bored with writing Maritza Rivera and hearing nothing back about the Parks dept.
    I’m loving what the community has done at the downtown Wedgwood park – what could we do at Dahl field?
    I’d walk around with another petition even though I don’t think they do anything.